Bowie County
US 259 – At Red River north of De Kalb, constructing new bridge.
US 259 – From US 82 to FM 44, adding shoulders.
FM 1297 – From FM 2878 to FM 559, widening highway.
Camp County
None
Cass County
None
Harrison County
I-20 Westbound – From SH 43 to Gregg County Line, repairing pavement. Various lane closures, expect delays.
FM 2625 – From SH 43 to 0.5 mile west, constructing mine haul road overpass.
US 59 – From SH 43 South to I-20 in Marshall, resurfacing highway
Marion County
None
Morris County
None
Panola County
SH 149 – At SH 315, constructing overpass and widening highway.
US 59 – At US 79 overpass, replacing bridge rails. Traffic reduced to one lane each direction.
SH 149 – From Rusk County Line to FM 124, resurfacing highway.
Titus County
US 271 – From end of freeway section of US 271 to 0.3 mile south of FM 3417, extending freeway lanes and constructing overpass at FM 3417.
US 271 – At Ripley Creek and Ripley Creek Relief, replacing bridges.
Upshur County
SH 155 – From south of Sabine River to US 80, replacing bridges and widening roadway.